What
The overall work includes sanitary sewer and storm sewer lining, selected sanitary lateral replacement, watermain replacement, curb and sidewalk replacement, additional street lighting, and road resurfacing.
Where and When:
Construction is planned for the following streets, as outlined in the map to the right:
- Agar Avenue,
- Davey Boulevard, and
- Miller Park Avenue (from Holland Street to Magani Avenue)
Work will commence on October 20, 2023, with an anticipated completion date of November 2024. The work planned for 2023 includes the structural lining of the storm and sanitary sewers, and sanitary lateral replacement. The remaining work is planned to begin in Spring 2024.
What to Expect Before Construction
Work crews will mark the locations of underground utilities including, gas, water, and cable to ensure the construction work does not interfere with these utilities.
Before the work begins, property owners should remove items located within the Town property (boulevard) limits including, landscaping and or decorative fencing or objects, before the work starts. If you have a sprinkler system within the boulevard, please contact Town staff (listed below).
How you may be Affected
General traffic and water supply: |
All roads will remain open throughout the project but there will be traffic detours around construction zones which may cause some delays. Occasionally, for short periods of time, we may restrict access to driveways to facilitate road, sidewalk, and curb construction works in front of your home. In these instances, we will work directly with you to facilitate access to your property and provide parking alternatives. In the event of a planned disruption to your water supply, we will share a notice at least 24 hours before the disruption. |
Residents within the construction area: |
Waste Collection:
Permission to Enter:
Accommodation:
Parking:
|
We thank you for your cooperation and apologize for any inconvenience this work may cause. Should you have any further questions or concerns, please contact the undersigned.